2003 Projects
2003 Projects
Go To 2003 Interactive Map
Mount Gallant Rd.
SC Highway 5/Reservation Rd. Intersection
Bird St./University Dr. Intersection
SC Highway 49/Paraham Rd. Intersection
SC Highway 55/Rhyne Rd Intersection
Mount Gallant Road/Paraham Rd. Intersection
SC Hwy 321/Ferguson Ridge Rd./Ridge Rd. Intersect
Porter Rd./Firetower Rd. Intersection
Shiloh Rd./SC Highway 5 Intersection
SC Highway 324/Cameron Rd./Gordon Rd. Intersection
Rawlinson Rd.
SC Highway 55 East of Clover
Fort Mill Southern By-pass
SC Highways 49/211/97/Nimitz Rd. Loop
Tega Cay/Gold Hill Rd. Connector
Adnah Church Rd/SC Hwy 161/SC Hwy 274 Intersection
Adnah Church Rd./SC Hwy 5/Eastview Rd Intersection
Eastview Rd./McConnells Hwy/Falls Rd. Intersection
Falls Rd./Robertson Rd. Intersection
Robertson Rd./Neely Rd. Intersection
US Hwy 21 (End of Cherry Rd. 5-lane to Sutton Rd.)
Gravel Road Group 1
Gravel Road Group 2
White St. Realignment and Railroad Crossing
McConnells Hwy (Heckle Blvd. to SC Highway 324)
Mt. Gallant Rd. (Dave Lyle Blvd. to Anderson Rd.)
SC Highway 557 (Kingsburry Rd. to SC Highway 49)
Ebinport Rd. (Cherry Rd. to India Hook Rd.)
SC Hwy 160(Springfield Pkwy to Lancaster Cty Line)
Riverview Rd. (Eden Terrace to SC Highway 161)
SC Highway 72 (SC Highway 901 to Rambo Rd.)
Mount Gallant Rd (Celanese Rd. to Twin Lakes Rd.)
SC Highways 274/279 (Pole Branch Rd.)
Ebenezer Rd. (Frank Gaston Blvd. to SC Hwy 161)
Springhill Farm Rd (SC Highway 51 to US Hwy 21)
SC Highway 51 (US Highway 21 to NC State Line)
Eden Terrace Rd. (Bradley St. to Anderson Rd.)
SC Highway 160 (Gold Hill Rd. to Zoar Rd)
  
Fort Mill Southern By-pass

 

 

03-004
Fort Mill Southern Bypass
 
Design Engineer
  • STV/Ralph Whitehead Associates – Rock Hill, SC
Contractor
  • Phase 1A: Callahan Grading – York, SC
  • Phase 1B: To be determined
  • Phase 1C: To be determined
  • Phase 2: To be determined
Schedule
  • Right-of-Way acquisition:           
    • Phase 1A: Complete
    • Phase 1B: Complete Fall 2011
    • Phase 1C: Complete late 2011/Early 2012
    • Phase 2: Complete Summer 2012
 Construction:
    • Phase 1A: Complete
    • Phase 1B: Start late 2011
    • Phase 1C: Start Spring 2012
    • Phase 2: Start Late 2012

Status

  • Construction of Phase 1A is complete. 

 Public Hearing Handouts and Exhibits (8/3/10):

Information packets

Overall project map

Map of Phase I

Map of Phase II

Existing and Concept Renderings - Dobys Bridge Road area

Existing and Concept Renderings - Legion Road area

Typical Sections


 You may contact the project team by mail, telephone, fax or e-mail as follows: 

York County Engineering
P.O. Box 148
York, SC 29745
Phone: (803) 684-8571
Fax: (803) 684-8596
Email:
engineering@yorkcountygov.com

 

 

 

 

 

 Print