03-004
Fort Mill Southern Bypass
Design Engineer
- STV/Ralph Whitehead Associates – Rock Hill, SC
Contractor
- Phase 1A: Callahan Grading – York, SC
- Phase 1B: To be determined
- Phase 1C: To be determined
- Phase 2: To be determined
Schedule
- Right-of-Way acquisition:
- Phase 1A: Complete
- Phase 1B: Complete Fall 2011
- Phase 1C: Complete late 2011/Early 2012
- Phase 2: Complete Summer 2012
Construction:
-
- Phase 1A: Complete
- Phase 1B: Start late 2011
- Phase 1C: Start Spring 2012
- Phase 2: Start Late 2012
Status
- Construction of Phase 1A is complete.
Public Hearing Handouts and Exhibits (8/3/10):
Information packets
Overall project map
Map of Phase I
Map of Phase II
Existing and Concept Renderings - Dobys Bridge Road area
Existing and Concept Renderings - Legion Road area
Typical Sections

You may contact the project team by mail, telephone, fax or e-mail as follows:
York County Engineering
P.O. Box 148
York, SC 29745
Phone: (803) 684-8571
Fax: (803) 684-8596
Email: engineering@yorkcountygov.com